Project Overview
Water, sanitary sewer, drainage, and concrete paving improvements for Sterling Traditions Sections 1 & 3.
Scope of Work
- Water distribution system installation
- Sanitary sewer installation
- Storm sewer and drainage improvements
- Reinforced concrete box culvert installation
- Storm manholes, junction boxes, and inlets
- Concrete paving and roadway construction
- Lime-flyash stabilized subgrade preparation
- Concrete curbs, sidewalks, and ADA ramps
- Trench safety and dewatering
- SWPPP controls, construction staking, grading, and site cleanup
“Self-performed civil from clearing through final paving — one schedule, one foreman, one number.”
Project Timeline
- ✓ Complete · Q2 2026Mobilization & Site Preparation
Mobilize crews and equipment, prepare the site, complete construction staking, install SWPPP controls, and begin clearing and grading.
- ✓ Complete · Q2 2026Water & Sanitary Sewer
Install water distribution lines, valves, flushing assemblies, sanitary sewer pipe, manholes, service leads, trench safety, and dewatering.
- ● Active · Q2–Q3 2026Drainage Improvements
Install storm sewer, reinforced concrete box culverts, storm manholes, junction boxes, inlets, groundwater control, and drainage connections.
- Upcoming · Q3 2026Paving & Closeout
Complete stabilized subgrade, reinforced concrete paving, curbs, sidewalks, ADA ramps, traffic control devices, final grading, and cleanup.