MOVING DIRT · BUILDING ROADS · DEVELOPING COMMUNITIESBUILD YOUR CAREER WITH A FAMILY-OWNED HOUSTON CONTRACTOR832-409-5740WE ARE HIRING: Fuel Lube Truck Drivers, PM Mechanics, Foremen, Superintendents, CDL Water Truck Drivers, Estimators, and Operators.MOVING DIRT · BUILDING ROADS · DEVELOPING COMMUNITIESBUILD YOUR CAREER WITH A FAMILY-OWNED HOUSTON CONTRACTOR832-409-5740WE ARE HIRING: Fuel Lube Truck Drivers, PM Mechanics, Foremen, Superintendents, CDL Water Truck Drivers, Estimators, and Operators.
NorthTex Construction
Home/Projects/Barret Crossing Sec.2
● Active Jobsite

Barret Crossing Sec.2

Detention, utilities, storm drainage, paving, and site restoration for a residential subdivision.

Budget
$5.6M
Timeline
7 months
Team
20–35 personnel
Scope
Detention, utilities, storm drainage, paving, and site restoration for a residential subdivision.
Status
Active
Client
Lago Bello Municipal Utility District No. 1A

Project Overview

Detention, utilities, storm drainage, paving, and site restoration for a residential subdivision.

Water Line
8-inch and 12-inch C900 PVC waterline
Wastewater
8-inch SDR-26 sanitary sewer
Storm Sewer
RCP storm sewer up to 60-inch
Paving
Reinforced concrete pavement, curbs, sidewalks, ramps, and grading
Detention
Phase Two detention facilities and detention basin excavation

Scope of Work

  • Clearing, grubbing, and site preparation
  • Phase Two detention basin construction
  • Amenity lake excavation and dewatering
  • Storm sewer installation
  • Storm junction boxes, inlets, manholes, and swales
  • Water distribution system installation
  • Wastewater collection system installation
  • Trench safety and dewatering
  • Concrete paving, curbs, sidewalks, and ramps
  • SWPPP, erosion control, turf establishment, and site restoration
“Self-performed civil from clearing through final paving — one schedule, one foreman, one number.”

Project Timeline

  1. ✓ Complete · Q1 2026
    Mobilization & Site Preparation

    Mobilize crews and equipment, begin clearing and grubbing, prepare access, install SWPPP controls, and start site layout.

  2. ✓ Complete · Q1–Q2 2026
    Detention & Earthwork

    Construct Phase Two detention facilities, complete basin excavation, amenity lake excavation, dewatering, swales, and major earthwork.

  3. ● Active · Q2–Q3 2026
    Water, Wastewater & Storm Sewer

    Install water distribution, wastewater collection, storm sewer, inlets, manholes, junction boxes, trench safety, and dewatering systems.

  4. Upcoming · Q3–Q4 2026
    Paving, Restoration & Closeout

    Complete concrete paving, curbs, sidewalks, ramps, SWPPP cleanup, turf establishment, final grading, and project closeout.

/05Outcomes

What we delivered.

Utilities
Infrastructure
Water, wastewater, and storm sewer
Paving
Roadway
Concrete pavement and curbs

Building something
like this?

If you have a similar scope to bid, send us your drawings and target schedule. We respond inside 48 hours.