MOVING DIRT · BUILDING ROADS · DEVELOPING COMMUNITIESBUILD YOUR CAREER WITH A FAMILY-OWNED HOUSTON CONTRACTOR832-409-5740WE ARE HIRING: Fuel Lube Truck Drivers, PM Mechanics, Foremen, Superintendents, CDL Water Truck Drivers, Estimators, and Operators.MOVING DIRT · BUILDING ROADS · DEVELOPING COMMUNITIESBUILD YOUR CAREER WITH A FAMILY-OWNED HOUSTON CONTRACTOR832-409-5740WE ARE HIRING: Fuel Lube Truck Drivers, PM Mechanics, Foremen, Superintendents, CDL Water Truck Drivers, Estimators, and Operators.
NorthTex Construction
Home/Projects/East T.C. Jester Stormwater Detention Basin
● Active Jobsite

East T.C. Jester Stormwater Detention Basin

This is a stormwater detention basin / flood control project for the Harris County Flood Control District.

Budget
$1.9M
Timeline
11 months
Team
8–15 personnel
Scope
Heavy civil construction services for the East T.C. Jester Stormwater Detention Basin project
Status
Active
Client
Harris County Flood Control District

Project Overview

This is a stormwater detention basin / flood control project for the Harris County Flood Control District. The work includes excavation and clearing for Detention Basin 1B, creating a wet-bottom detention basin, side slopes, maintenance berm, access improvements, outlet/outfall drainage work, hydroseeding, concrete driveways, manholes, riprap, and related site restoration

Project Type
Stormwater detention / flood control
Delivered
Q1 2027 estimated
Location
East T.C. Jester area, Harris County, TX
Earthwork
Excavation, clearing, grading, haul-off, and basin shaping
Concrete
Concrete driveways, concrete truck washout structures, and drainage-related concrete items
Detention
Wet-bottom stormwater detention basin

Scope of Work

  • Excavation and clearing
  • Stormwater detention basin construction
  • Site grading and material disposal
  • Stabilized access road / construction access
  • Concrete driveways and washout structures
  • Riprap and slope protection
  • Hydroseeding and turf establishment
  • Erosion control and site restoration
“Self-performed civil from clearing through final paving — one schedule, one foreman, one number.”

Project Timeline

  1. ✓ Complete · Q2 2026
    Mobilization & Site Prep

    Mobilize equipment, install erosion controls, establish construction access, and prepare the detention basin work area.

  2. ● Active · Q2–Q3 2026
    learing & Excavation

    Clear the work area, excavate the stormwater detention basin, haul off excess material, and begin rough grading.

  3. Upcoming · Q3–Q4 2026
    Basin Construction & Drainage Improvements

    Shape basin slopes, install drainage-related improvements, concrete access items, riprap, and slope protection.

  4. Upcoming · Q4 2026–Q1 2027
    Stabilization & Final Restoration

    Complete final grading, hydroseeding, turf establishment, erosion control cleanup, and final site restoration.

/05Outcomes

What we delivered.

Flood
Infrastructure improvement
Stormwater detention and drainage capacity
1
Stormwater detention basin
Wet-bottom basin construction
350
Calendar days
Project schedule
$1.9M
Project value
Harris County Flood Control District

Building something
like this?

If you have a similar scope to bid, send us your drawings and target schedule. We respond inside 48 hours.