MOVING DIRT · BUILDING ROADS · DEVELOPING COMMUNITIESBUILD YOUR CAREER WITH A FAMILY-OWNED HOUSTON CONTRACTOR832-409-5740WE ARE HIRING: Fuel Lube Truck Drivers, PM Mechanics, Foremen, Superintendents, CDL Water Truck Drivers, Estimators, and Operators.MOVING DIRT · BUILDING ROADS · DEVELOPING COMMUNITIESBUILD YOUR CAREER WITH A FAMILY-OWNED HOUSTON CONTRACTOR832-409-5740WE ARE HIRING: Fuel Lube Truck Drivers, PM Mechanics, Foremen, Superintendents, CDL Water Truck Drivers, Estimators, and Operators.
NorthTex Construction
Home/Projects/Midline Phase 2
● Active Jobsite

Midline Phase 2

Mass grading, detention, and drainage improvements with excavation, storm sewer, dewatering, and site restoration.

Budget
$7.6M
Timeline
8 Months
Team
15–25 personnel
Scope
Mass grading, detention, and drainage improvements with excavation, storm sewer, dewatering, and site restoration.
Status
Active
Client
Baybrook Municipal Utility District No. 1

Project Overview

Drainage, detention, and mass grading improvements for Midline Phase 2, including excavation, embankment, storm sewer, box culverts, swales, dewatering, seeding, and site restoration.

Earthwork
Mass grading, excavation, embankment, and fill placement
Detention
Detention pond excavation and grading
Drainage
Storm sewer, swales, box culverts, and drainage structures
Restoration
Seeding, final grading, and site cleanup

Scope of Work

  • Mass grading and excavation
  • Detention pond construction
  • Embankment and fill placement
  • Storm sewer installation
  • Reinforced concrete box culverts
  • Interceptor swales and drainage grading
  • Dewatering and surface water control
  • Removal of existing utilities and structures
  • Seeding, erosion control, and site restoration
  • As-built survey and project closeout
“Self-performed civil from clearing through final paving — one schedule, one foreman, one number.”

Project Timeline

  1. ✓ Complete · Q1 2026
    Mobilization & Site Preparation

    Mobilize crews and equipment, establish access, install SWPPP controls, and prepare the site for mass grading and drainage construction.

  2. ● Active · Q1–Q2 2026
    Mass Grading & Earthwork

    Complete excavation, embankment, fill placement, removal of existing items, and rough grading for Midline Phase 2.

  3. ● Active · Q2–Q3 2026
    Detention & Drainage Improvements

    Construct detention pond areas, install storm sewer, drainage structures, interceptor swales, and reinforced concrete box culverts.

  4. Upcoming · Q3–Q4 2026
    Final Grading & Closeout

    Complete final grading, seeding, erosion control cleanup, as-built survey, site restoration, and project closeout.

/05Outcomes

What we delivered.

Detention
Stormwater
Pond excavation and grading
Drainage
Infrastructure
Storm sewer, swales, and box culverts
Mass Grading
Earthwork
Excavation and embankment