Project Overview
Water, wastewater, storm drainage, and paving improvements for Grace Landing Section Two, including utility installation, storm sewer, trench safety, dewatering, SWPPP controls, and site restoration.
Scope of Work
- Site preparation and stripping
- Water distribution system installation
- Water valves, hydrants, services, and connections
- Wastewater collection system installation
- Sanitary sewer manholes and service leads
- Storm sewer installation
- Storm sewer inlets, manholes, and junction boxes
- Trench safety and dewatering
- Concrete paving, curbs, ramps, and grading
- SWPPP compliance and site restoration
“Self-performed civil from clearing through final paving — one schedule, one foreman, one number.”
Project Timeline
- ✓ Complete · Q2 2026Mobilization & Site Preparation
Mobilize crews and equipment, prepare the site, remove existing materials, install SWPPP controls, and begin construction layout.
- ● Active · Q2 2026Water & Wastewater Installation
Install waterlines, valves, hydrants, water services, sanitary sewer pipe, manholes, and service leads.
- ● Active · Q2–Q3 2026Storm Sewer & Drainage Improvements
Install RCP storm sewer, storm inlets, manholes, junction boxes, trench safety, and dewatering systems.
- Upcoming · Q3 2026Paving, Restoration & Closeout
Complete concrete paving, curbs, ramps, grading, SWPPP cleanup, testing, final restoration, and project closeout.