MOVING DIRT · BUILDING ROADS · DEVELOPING COMMUNITIESBUILD YOUR CAREER WITH A FAMILY-OWNED HOUSTON CONTRACTOR832-409-5740WE ARE HIRING: Fuel Lube Truck Drivers, PM Mechanics, Foremen, Superintendents, CDL Water Truck Drivers, Estimators, and Operators.MOVING DIRT · BUILDING ROADS · DEVELOPING COMMUNITIESBUILD YOUR CAREER WITH A FAMILY-OWNED HOUSTON CONTRACTOR832-409-5740WE ARE HIRING: Fuel Lube Truck Drivers, PM Mechanics, Foremen, Superintendents, CDL Water Truck Drivers, Estimators, and Operators.
NorthTex Construction
Home/Projects/Creek Haven Sec 4
Delivered

Creek Haven Sec 4

Water, sanitary sewer, and storm drainage improvements with trench safety, dewatering, and site restoration.

Budget
$2.8M
Timeline
3 Months
Team
12–20 personnel
Scope
Water, sanitary sewer, and storm drainage improvements with trench safety, dewatering, and site restoration.
Status
Complete
Client
Brazoria County Municipal Utility District No. 92

Project Overview

Water, sanitary sewer, and storm drainage improvements for Creekhaven Section 4, including utility installation, manholes, storm sewer, inlets, trench safety, dewatering, testing, and site restoration.

Scope of Work

  • 8-inch sanitary sewer installation
  • Sanitary sewer service leads
  • Sanitary manholes and drop connections
  • CCTV inspection and testing
  • 8-inch waterline installation
  • Water services, valves, and flush assemblies
  • Storm sewer installation
  • Storm inlets and manholes
  • Trench safety and dewatering
  • SWPPP, erosion control, seeding, and site restoration
“Self-performed civil from clearing through final paving — one schedule, one foreman, one number.”

Project Timeline

  1. ✓ Complete · Q1 2026
    Sanitary Sewer & Waterline Installation

    Install sanitary sewer, service leads, manholes, 8-inch waterline, valves, water services, and flush assemblies.

  2. ✓ Complete · Q1–Q2 2026
    torm Sewer & Drainage Improvements

    Install RCP storm sewer, inlets, manholes, trench safety, dewatering, and drainage structures.

  3. ✓ Complete · Q2 2026
    Testing, Restoration & Closeout

    Complete CCTV inspection, utility testing, erosion control cleanup, seeding, site restoration, as-builts, and final closeout.

/05Outcomes

What we delivered.

5,328 LF
Sanitary Sewer
8-inch sanitary line
5,720 LF
Water Line
8-inch C900 waterline
Residential
Property Type
Section 4 land development

Building something
like this?

If you have a similar scope to bid, send us your drawings and target schedule. We respond inside 48 hours.