MOVING DIRT · BUILDING ROADS · DEVELOPING COMMUNITIESBUILD YOUR CAREER WITH A FAMILY-OWNED HOUSTON CONTRACTOR832-409-5740WE ARE HIRING: Fuel Lube Truck Drivers, PM Mechanics, Foremen, Superintendents, CDL Water Truck Drivers, Estimators, and Operators.MOVING DIRT · BUILDING ROADS · DEVELOPING COMMUNITIESBUILD YOUR CAREER WITH A FAMILY-OWNED HOUSTON CONTRACTOR832-409-5740WE ARE HIRING: Fuel Lube Truck Drivers, PM Mechanics, Foremen, Superintendents, CDL Water Truck Drivers, Estimators, and Operators.
NorthTex Construction
Home/Projects/Chimney Rock Road
● Active Jobsite

Chimney Rock Road

Roadway construction project for Chimney Rock Road, Segment Two, from American Canal to McHard Road. The work includes the materials, labor, equipment, tools, services, and supervision needed to complete the road construction project for Fort Bend County

Budget
$16.4M
Timeline
17 months
Team
25–40 personnel
Scope
Roadway, bridge, drainage, pump station, and utility improvements
Status
Active
Client
Fort Bend County, Texas

Project Overview

Northtex Construction is providing heavy civil construction services for the Chimney Rock Road Construction project from American Canal to McHard Road, Segment Two, for Fort Bend County. The scope includes roadway construction, site preparation, earthwork, underground drainage utilities, storm sewer and box culvert work, pump station-related work, dewatering, concrete structures, paving improvements, traffic/control coordination, labor, equipment, materials, supervision, and project completion in accordance with the County’s plans and specifications.

Client
Fort Bend County, Texas
Location
Fort Bend County, Texas
Bridge Span
2 bridges over American Canal
Concrete Pour
8-inch reinforced concrete pavement
Status
In Progress
Delivery
Q3 2026

Scope of Work

  • Roadway construction and paving
  • Bridge construction over American Canal
  • Storm sewer and drainage improvements
  • Pump station-related work
  • Underground utility coordination
  • Concrete drainage structures
  • Dewatering and trench safety
  • Traffic control and site restoration
“Self-performed civil from clearing through final paving — one schedule, one foreman, one number.”

Project Timeline

  1. ✓ Complete · Q1 2025
    Mobilization & Site Preparation

    Mobilize crews and equipment, install traffic controls, prepare work zones, and begin site coordination.

  2. ✓ Complete · Q2–Q3 2025
    arthwork, Utilities & Drainage

    Complete roadway excavation, underground drainage improvements, storm sewer work, dewatering, and utility coordination.

  3. ● Active · Q4 2025–Q2 2026
    Bridge, Pump Station & Concrete Work

    Construct bridge structures, pump station-related improvements, concrete drainage structures, and roadway pavement sections.

  4. Upcoming · Q3 2026
    Final Paving, Restoration & Closeout

    Complete final paving, striping, site restoration, inspections, punch list, and project closeout.

/05Outcomes

What we delivered.

Public
Infrastructure
County mobility bond project
Roadway
Property Type
Public road construction
2
Bridge Structures
Northbound and southbound bridges over American Canal
547
Calendar Days
Project schedule

Building something
like this?

If you have a similar scope to bid, send us your drawings and target schedule. We respond inside 48 hours.